The Requirement
To provide the foundations for an extension, where the site posed the following challenges:
- Nearby trees and highly shrinkable clay soil meat that a piled solution was the only viable option.
- The restricted access down a set of steps mean that a system with lightweight, portable equipment was needed.
![](https://www.quadrabuild.com/wp-content/uploads/2017/06/3a-IMG_0421-650x520.jpg)
![](https://www.quadrabuild.com/wp-content/uploads/2017/06/4.-IMG_0429-650x520.jpg)
![](https://www.quadrabuild.com/wp-content/uploads/2017/06/5.-IMG_2493-650x520.jpg)
![](https://www.quadrabuild.com/wp-content/uploads/2017/06/1.-IMG_0416-650x520.jpg)
![](https://www.quadrabuild.com/wp-content/uploads/2017/06/2.-IMG_0419-650x520.jpg)
The Solution
- Installation of a QuadraPile solution with reinforced concrete ground beams was ideal.
- All the equipment could be carried down the steps by two operatives without needing any large machinery.
- Heave protection boards could be installed to allow the ground to move without affecting the structure of the building.
Case study reference: 16218