The Challenge

Foundations were required for a modular building at a sloping site which was difficult to access and surrounded by trees.

The Solution

We installed QuadraPile helical piles topped with steel brackets to take the steel base frame of the building.
The building was then lifted into position from a position further up the hill.

The small QuadraPile installation equipment was easily carried to the site and allowed the foundations to be created quickly and efficiently.
Small, portable load testing equipment was used to prove the capacity of the piles.